Juwi Renewable Energies (Pty) Ltd
Construction of a 6.9MW PV Farm near Malmesbury, Western Cape
Start Date: 04 December 2013
End Date: 30 April 2014
| EPC | Engineer (Company): | Juwi |
| EPC | Engineer: | Andreas Lukasczyk |
| EPC | Engineer (RE): | Kaloyan Dimov |
| Raubex Infra Operations Director: | Charles Deacon | |
| Raubex Infra Construction Manager: | Christo Taljaard | |
| Scope of Works: | ||
| Description: Civil and electrical balance of plant contractor for the construction of a 6.9MW PV Farm near Malmesbury, Western Cape | ||
| The works includes: | ||
| 1. | Site Preparation | |
| 2. | Electrified perimeter fence | |
| 3. | O & M building | |
| 4. | Storm water management | |
| 5. | Substations | |
| 6. | Overhead lines | |
| 7. | Electrical works including all installation, testing and commissioning, including but not limited to | |
| | - | Solar stringing of homerun cables |
| | - | Installation of string monitors |
| | - | Cable trenches, conduits, cable laying, terminating and testing |
| | - | Installation of inverters and transformer stations |
| | Main access and internal service roads | |
| | ||