Kentha Developers (Pty) Ltd
Hillside view Phase 2, Bloemfontein, Free State, South Africa
Start Date: 02 December 2015
End Date: 29 September 2016
| Raubex Infra Operations Director: | Ean Steenkamp | |
| Raubex Infra Construction Manager: | Jaco Fick | |
| Engineer (Company): | Bigen Africa | |
| | Engineer (Designer): | Gerda van der Merwe |
| Scope of Works: | |
| Description: Construction of a 355dia Sewer pump station rising main of +/- 2km in Hillside view Phase 2 | |
| 1. | Excavation and backfilling of trenches |
| 2. | Laying of the 355 dia UPVC cl 16 Pipe |
| 3. | Installation of air valves |
| 4. | Construction of valve and scour chambers |
| 5. | Connect to existing manhole |