Alcatel Lucent (Nokia)
Camps Bay, Cape Town, Western Cape, South Africa
Start Date: 20 November 2015
End Date: 30 November 2016
| Raubex Infra Operations Director: | Danie Marais |
| Raubex Infra Construction Manager: | Tjaard Booyens |
| Scope of Works: | |
| Description: Install Fibre to home for Alcatel Lucent in Camps Bay Cape Town for 960 houses. | |
| The works include: | |
| 1. | Trench excavation and reinstatement |
| 2. | Hauling of ducts |
| 3. | Cable Floating |
| 4. | Construct manholes |
| 5. | Cable splicing |
| 6. | Install aerial cable |
| 7. | Splicing test |