Lufhereng Development Company (Pty) Ltd
Lufereng Housing Development, Protea Glen, Soweto, Gauteng, South Africa
Start Date: 01 October 2020
End Date: 10 December 2021
| Client Representative | Hannes Potgieter | |
| Raubex Infra Operations Director: | Andries Swart | |
| Raubex Infra Commercial Manager: | Nikki Carnicelli | |
| Raubex Infra Construction Manager: | Brandon Kalil | |
| Engineer (Company): | Bigen Africa | |
| | Engineer (Design): | Andre Wesson & Dieter Storbeck |
| | Engineer (RE): | Sikho Sikhosana |
| Scope of Works: | ||
| Description: Civil engineering services for Lufhereng Extensions 9,10 and 11 including roads, stormwater, sewer and water infrastructure consisting of approximately 5000 residential units and supportive land uses. | ||
| The works include: | ||
| 1. | Installation of HDPE sewer reticulation network | |
| | - | By means of butt welding |
| | - | Sewer manholes and valve boxes |
| | - | Associated earthworks |
| | - | Erf connections |
| | - | CCTV sewer reticulation network |
| 2. | Installation of HDPE water reticulation network: | |
| | - | By means of butt welding |
| | - | Erf connections |
| | - | Associated earthworks |
| | - | Pressure testing of network |
| 3 | Installation of storm water network | |
| | - | Spigot and socket pipe network of various sizes |
| | - | Link storm water culverts of various sizes including structures |
| | - | Kerb inlet structures and junction boxes |
| 4 | Internal & Link Roads | |
| | - | All layer works and associated tests |
| | - | Upgrading existing provincial road intersections |
| | - | Road signs and marking |
| | - | Pedestrian crossings |