Copperton Wind Farm (RF) Proprietary Limited (Elwan)
Copperton, Northern Cape, South Africa
Start Date: 21 August 2018
End Date: 18 January 2022
| Project Managers: | Elwan |
| | Carlos Rodriquez |
| Engineer: | Thabile |
| | Louis du Toit |
| Contract Manager: | Charles Deacon |
| Construction Manager: | Chris de Waal |
| Date of Award: | 21 August 2018 |
| Completion Date: | 18 January 2022 |
| Contract Period | 42 Months |
| Description: Engineering and Design of civil and electrical balance of plant for a 102MW Wind Energy Facility (WEF) The Works Include:
| |