Kentha Developers (Pty) Ltd
Hillside view Phase 2, Bloemfontein, Free State, South Africa
Start Date: 02 December 2015
End Date: 29 September 2016
Raubex Infra Operations Director: | Ean Steenkamp | |
Raubex Infra Construction Manager: | Jaco Fick | |
Engineer (Company): | Bigen Africa | |
| Engineer (Designer): | Gerda van der Merwe |
Scope of Works: | |
Description: Construction of a 355dia Sewer pump station rising main of +/- 2km in Hillside view Phase 2 | |
1. | Excavation and backfilling of trenches |
2. | Laying of the 355 dia UPVC cl 16 Pipe |
3. | Installation of air valves |
4. | Construction of valve and scour chambers |
5. | Connect to existing manhole |