Pennyville Zamimphilo Relocations (Pty) Ltd / Calgro M3 Holdings
Vista Park, Bloemfontein, Free State, South Africa
Start Date: 03 May 2022
End Date: 04 July 2023
Client Representative: | Deon Steyn |
Raubex Infra Project Manager: | Nikki Carnicelli |
Raubex Infra Construction Manager: | Siphosihle Madliwa |
Engineer (Company): | Bigen Africa |
Engineer: | Andre Wesson |
Scope of Works: | ||
Description: Construction of civil Engineering Services for 204 erf stands and link roads for Vista Park Extension 257, 262, 263 | ||
The works include: | ||
1. | Link and internal roads and associated reserves | |
| - | Internal road reserves of 13m with 2.5m roadway widths |
| - | Internal road reserves of 16m with 3.7m roadway widths |
| - | Link road reserves of 20m with 3.7m roadway widths |
| - | Kerbing, channelling & segmented paving |
| - | Layer works including subgrade, subbase, base & asphalt surfacing |
| - | Installation of cable ducts for electrical reticulation road crossings |
2. | Stormwater infrastructure for link and internal roads | |
| - | Storm water channels |
| - | Storm water network - 450mmØ to 825mmØ |
| - | Kerb and drop inlet stormwater structures and junction boxes |
| - | Associated earthworks |
3. | Installation of UPVC street front sewers consisting of: | |
| - | 160mmØ -200mmØ pipes with precast concrete manholes |
| - | Associated earthworks |
4 | Installation of UPVC water mains in street reserves consisting of: | |
| - | 110mmØ – 200mmØ pipes |
| - | 110mm UPVC ducts for house connections in road crossings |
| - | Connection to existing link water line |
| - | Erf connections |
| - | Associated earthworks |