Western Cape Department of Human Settlements
Pacaltsdorp, George, Western Cape
Start Date: 01 August 2018
End Date: 31 October 2019
Client Representative: | Charl Louw |
Raubex Infra Operations Director: | Danie Marias |
Raubex Infra Construction Manager: | Danie Marias |
Engineer (Company): | Royal Haskoning DHV |
Engineer: | Keith Turner |
Engineer (RE): | Pieter Joubert |
Scope of Works: | ||
Description: Construction of civil engineering services and 176 (Finance Linked Individual Subsidy Programme) FLISP housing units. | ||
The works include: | ||
1. | Civil engineering services | |
| - | Sewer network and house connections |
| - | Water reticulation network and house connections with municipal meters |
| - | Internal & bus roads with associated, signage, marking, kerbs, paving and stormwater network |
| - | Provision for future electrical house connections |
2. | 176 Housing units | |
| - | Housing units with final finishes |
| - | Boundary wall for each unit |